EOLMED project

Archimed therefore acts as a subcontractor on several aspects of the EOLMED project.

  • The floating steel foundations will be prefabricated in the Matière factories of Bagnac-sur-Célé and the Creusot.
  • The blocks will then be transported to Port-la-Nouvelle, where Ponticelli’s teams will assemble them. A float consists of 92 blocks.

The float-off is planned for summer 2024.

The Port-La-Nouvelle assembly site will thus bring together several trades and know-how such as:

  • fitters and welders,
  • scaffolders,
  • painting and lifting operators,
  • electrical and instrumentalization technicians
  • as well as technicians and operators for launching floats.